Serving the people of Oundle

Anglian Water - Planned work Glapthorn and New Road

Anglian Water - Planned work Glapthorn and New Road

Anglian Water work is necessary work to resolve two issues;

  • To renew the water main along New Road to reduce the amount of burst clusters.
  • To increase the flow and pressure into the Cotterstock Road/St Peter's Road area by laying a reinforcement main along Pavilion Drive and 100 meters along Glapthorn Road.

Here are the maps of the work Anglian Water will be carrying out on Glapthorn and New Road completed in 3 phases.

- Phase 1 Start 3rd July 2023 End 1st September 2023

- Phase 2 Start 4th September 2023 End 12th January 2024

- Phase 2 Start 15th January 2024 End 5th April 2024

For more information about this work contact Anglian Water 0345 791 9155

Posted: Mon, 26 Jun 2023 17:02 by Rebecca

Tags: Update